⬆ Back to PMO Toolkit


Gantt Chart / Project Schedule

Sequences every activity by duration, dependency type, and due date so the critical path — and the impact of a slipped task — is visible before it happens. Built for the Project Monitoring Dashboard project.

Phase Summary

Phase Duration Due Date Dependency Logic
1. Initiation 13 days 10–17 Jun 2026 Sequential Finish-to-Start chain
2. Planning 19 days 22 Jun–11 Jul 2026 Parallel tracks
3. Execution 5 days 14 Jul–01 Aug 2026 Finish-to-Start chain
4. Control Runs in parallel throughout — Start-to-Start, asynchronous
5. Closure Post-event to 22 Aug 2026 Finish-to-Start / Finish-to-Finish

Milestone Summary

Milestone Trigger Date Success Criteria
M1 — Initiation Complete 19 Jun 2026 Event dates/platform confirmed
M2 — Planning & Peer Review Gate 11 Jul 2026 Sign-off to transition into execution
M3 — Platform Readiness Verification 27 Jul 2026 Successful dry run
M4 — Forum Event Delivery Completed 01 Aug 2026 All core educational streams executed
M5 — Project Closure & Handover 22 Aug 2026 Final institutional sign-off

Uses FS (Finish-to-Start), SS (Start-to-Start), and FF (Finish-to-Finish) dependency logic to model parallel control activities alongside a sequential critical path.

The Mobile Stage Pros project runs a simpler three-phase, 90-day cadence tracked directly on the Monday.com Dashboard — see also the WBS.