Sequences every activity by duration, dependency type, and due date so the critical path — and the impact of a slipped task — is visible before it happens. Built for the Project Monitoring Dashboard project.
| Phase | Duration | Due Date | Dependency Logic |
|---|---|---|---|
| 1. Initiation | 13 days | 10–17 Jun 2026 | Sequential Finish-to-Start chain |
| 2. Planning | 19 days | 22 Jun–11 Jul 2026 | Parallel tracks |
| 3. Execution | 5 days | 14 Jul–01 Aug 2026 | Finish-to-Start chain |
| 4. Control | Runs in parallel throughout | — | Start-to-Start, asynchronous |
| 5. Closure | Post-event | to 22 Aug 2026 | Finish-to-Start / Finish-to-Finish |
| Milestone | Trigger Date | Success Criteria |
|---|---|---|
| M1 — Initiation Complete | 19 Jun 2026 | Event dates/platform confirmed |
| M2 — Planning & Peer Review Gate | 11 Jul 2026 | Sign-off to transition into execution |
| M3 — Platform Readiness Verification | 27 Jul 2026 | Successful dry run |
| M4 — Forum Event Delivery Completed | 01 Aug 2026 | All core educational streams executed |
| M5 — Project Closure & Handover | 22 Aug 2026 | Final institutional sign-off |
Uses FS (Finish-to-Start), SS (Start-to-Start), and FF (Finish-to-Finish) dependency logic to model parallel control activities alongside a sequential critical path.
The Mobile Stage Pros project runs a simpler three-phase, 90-day cadence tracked directly on the Monday.com Dashboard — see also the WBS.